We are now approaching the initial startup phase of the project.
Our first step will be to bring in the initial seeding material for the digesters, this will involve approximately 15-17 HGV deliveries per day of material arriving at site for ~15 days.
This process will begin at the end of May/beginning of June.
Following the initial seeding we expect to begin producing biogas through June with anticipated biomethane injection to the gas grid following in July.
We do not anticipate this initial seeding or startup phase causing any issues to the wider community, but should you have any concerns, please contact us at contact@wormsladegreenenergy.com
Vida Bioenergy